Delayed progress due to KDC building consent approval unfortunately pushed the end date past December. Adron has re-sequenced work and is in the process of  completing the internal fit out, linings and painting. Planning for the transition from the temporary facilities into the repaired clubhouse is underway. Equipment storage and the removal and selling of the temporary buildings and containers are now a priority.

All going well we should be back in our club early February followed by potential opening & blessing of the Clubhouse and Pā site.