Seawall and Boat Ramp Works update

10 Sep

Following Wharehine Construction's mobilisation in mid-August, the construction of the Seawall and Boat Ramp repair and upgrade has quickly accelerated and is well underway. Excellent weather and tides ensured that the first sections of the Seawall were constructed successfully and observed by key parties.

Meetings with Northland Regional Council (NRC), Kaipara District Council (KDC), the designer (LDE), MHVLS, Te Uri o Hau, site Archaeologist and Wharehine continue in these early stages to ensure the site team follows the design and respects the area's heritage. Wharehine started work from the southern end of the Seawall and had completed approximately 40% of the toe (base) by the end of August. Subgrade, geofabric, filter layer and bulk rip rap are following the toe construction when tides are higher.

It is expected that during September 90% of the Seawall toe (the focus during westerly dominated weather patterns) and 75% of the following subgrade, geofabric, filter layer and bulk rip rap layers will be complete.

Late in September, the site team will construct the temporary MHVLS boat ramp. This ramp will allow continual lifeguard and Search and Rescue operational access when the existing ramp to the beach is shut for repair and extension. At the same time (late September), the last public access point with steps down to the beach will close for public safety while work is completed. It is expected to be closed for approximately one month. 

MHVLS appreciates public support during these critical works and looks forward to being fully operational for the lifeguard season starting on Labour Day weekend.